Archive for the 'Lean Manufacturing' Category

The Total Impact of Off-shoring

Thursday, May 10th, 2007

Lately, I’ve been running into manufacturing companies that have off-shored much of their value stream. One company’s “China strategy” involves buying components from vendors and also building sub-assemblies at a company controlled plant in China.

That’s fine, and I certainly understand the compelling economics in some situations (for example, commodity items with high labor content). But too often, the visible savings with direct labor overshadows the less obvious yet greater wastes that are created. For example:

  • Less agility. As Bill Waddell wrote earlier, “you can’t pull from China“. Your ability to adjust to customer demand is compromised if your total lead times are four times longer.
  • More inventory.
  • More defects. Why? There’s a longer delay between defect creation upstream, and defect detection downstream.
  • More transportation.
  • More management costs. The effort to integrate operations overseas is usually underestimated.
  • Product development and launch. Lean product development principles require concurrent engineering and a minimum of knowledge “hand offs”.

I’m not saying that having an off-shore strategy means that a company is not lean. I am saying that having some of your value chain somewhere else in the world for the sole purpose of reducing direct labor costs is a huge red flag. Be sure you understand the significant waste, cost, and additional lead time that will be created as a direct consequence.

Identifying Waste in Your Business

Monday, February 19th, 2007

Eliminating waste, or muda, from processes is a core concept of lean. Most of us know the seven types of waste (see below), yet the trick is “learning to see” these wastes that often are ubiquitous parts of our operations. Below is a list of common symptoms for each waste. If you see the symptom, you may have an opportunity to eliminate the underlying waste.

  • Defects - Plant “hospitals”, rework loops, customer returns and complaints, cost overruns for raw materials or labor, 100% inspection (in plant or at the customer).
  • Overproduction - Often called the “mother of all muda” since it can cause or increase the incidence of the other six wastes. Look for excess inventory, AS/RS systems, large batch size, inability to meet customer demand, long or complex setups, low awareness of takt time (customer demand rate), poor quality, inflexibility, disjointed operations within a process.
  • Transportation - Fork lifts, carts, AR/RS systems, AGV systems, consumption of envelopes, boxes, shipping labels, long lead times, aisles, conveyors.
  • Waiting - Bins, queuing areas, waiting areas, chairs, in/out boxes, large batch sizes, long lead times, pallets, boxes, envelopes, stuff in the aisles.
  • Inventory - Look for reasons that people would build inventory as a quick fix to a problem: parts shortages, mura, defects, long lead times, labor standards, idle time, lack of clear build signal.
  • Motion - Safety issues like repetitive strain injuries, falls, long or inconsistent cycle times, misplaced tools, cranes, lifts and other material handling equipment
  • Overprocessing - Conformance issues with tolerances, fit, finish. Long cycle times, worker performance issues, scrap rates, standard material specifications

What’s the financial impact of missing a customer shipment?

Tuesday, February 13th, 2007

This is a recounting of a conversation I had with a plant manager about the financial impact of missing shipment of his product for that month (which since it was December, was also be a miss for the fiscal year). The lesson is an old one: be sure to do a marginal (incremental) analysis when assessing the impact of a change in revenue, cost, or profit, and be aware of how you handle allocated fixed costs.

Me: So you may miss shipment for 5 units this month? How will that impact the company financially?

Plant Manager: Well, cost accounting shows that the profit for this product is $50,000, so this may be a $250,000 hit to the company.

Me: I’m afraid the impact will be larger than that. $50,000 is the average profit per unit (writing on my tablet):

Profit = Revenue – Variable Costs – Allocated Fixed Costs

But, what’s the financial impact if you don’t ship a unit?

∆Profit = ∆Revenue - ∆VC - ∆FC

∆FC = 0 (these are fixed costs, and don’t vary with volume), so

∆Profit = ∆Revenue - ∆VC

So the impact to profit of not shipping a product is its incremental revenue less its incremental variable cost. You said that revenue per unit is $1,300,000 and its variable cost is $1,070,000, so the impact to profit of missing shipment will be $230,000 per unit.

PM: That’s over $1 million in lost profit for 5 units!

Me: Sorry to be the bearer of bad news, but remember that ∆Revenue - ∆VC is sometimes called “profit contribution” which is a significantly larger number than the “profit” that cost accounting attributes to a product.

And the impact to cash flow (what really gets some companies in a bind) may be even greater. For example, what if much of the raw materials for this product are already purchased and sitting in inventory?

The impact to Cash Flow (∆CF) would be:

∆CF = ∆Revenue - ∆VC + (inventory already purchased for that item)

PM: I get the idea, but I’m not even going to calculate that number. But I do have a heightened sense of the financial impact of not being able to ship a customer order.

Henry Ford on Continuous Improvement

Tuesday, February 13th, 2007

Henry Ford embarrassed himself later in life and left his company with a dark legacy surrounding his public and published anti-Semitism. He’s certainly no role model, but his genius for manufacturing is legendary, and he is easy, even fun, to read when he focuses on business. He had a gift for envisioning simple solutions to unsolved engineering and business issues.

As an example, here are excerpts from Ford’s My Life and Work (available from Amazon and B&N) that I categorized by current topics that challenge us still today:

Continuous improvement

Hardly a week passes without some improvement being made somewhere in machine or process…The factory keeps no record of experiments. The foremen and the superintendents remember what has been done.

Not a single operation is ever considered as being done in the best or cheapest way.

Try new processes

The saving on one style of bolt alone amounted to half a million dollars a year.

Engaging Everyone in Continuous Improvement

We get some of our best results from letting fools rush in where angels fear to tread.

None of our men are “experts.” The moment one gets into the “expert” state of mind a great number of things become impossible.

Target costing

We have never considered any costs as fixed. Our policy is to reduce the price, extend the operations, and improve the article. You will notice that the reduction of price comes first.

Adding Capacity

Monday, February 12th, 2007

Driven by our strong economy, many of our manufacturing clients have plans to increase production capacity. I sometimes share with them this strategy that Richard Schonberger describes in World Class Manufacturing:

Increase capacity in increments. If your sales forecast calls for increasing capacity by 100 widgets, start by adding a line that can handle 25. Then add separate lines as needed to handle growth.

This approach:

  • Lowers the risk of hiring too many people and over investing in capital equipment if the sales forecast is wrong.
  • Creates several parallel lines instead of one line. This improves flexibility, reduces the impact of a line going down, and simplifies new product introductions.

Client Example: Staying Close to Operations, Part 3

Thursday, February 8th, 2007

Our client continues describing how staying close to operations helped with their problem solving (see part 1 and part 2):

“We now understood that a root cause of our problems with delivery times and parts shortages is how we manage our logistics and signal delivery of parts from our suppliers. Our operations use an MRP system overall, with one exception: the assembly operations for one value stream implemented a simple pull process. So in effect, we now had two logistics processes, what our change agent calls an MRP/push process and a kanban/pull process.

“Not surprisingly most of our problems were within the value stream where we were using both: kanban/pull within assembly, and MRP for the supply chain. I felt I wanted operations to have a single, consistent logistics process across all value streams, but how do we get there? I was also getting a lot of push back from my Material organization; I had several key professionals who are CPIM certified, and felt strongly that a well designed and managed MRP system would be our safest, most proven approach. I was concerned how they would accept a different approach like a kanban/pull process. Would they help make it work, or try to prove that it was a poor decision?

“I finally decided to pilot a kanban/pull process across one entire value stream - the same value stream that was using kanban/pull for assembly. I felt we could learn from this experience without adversely disrupting our entire operations in case something went wrong. We had considerable discussion about preserving MRP as a “fall back” in case the kanban/pull effort did not work out, but our change agent encouraged us to be unequivocal about our decision and to be committed to the success of this pilot. In hindsight, the commitment of my staff, including Materials, was critical to success. Things things made this commitment possible:

- My ability to achieve alignment with the decision. This was achieved during a project planning session facilitated by our change agent. We learned the importance of all of us being committed to my decision, even though not every one agreed. [Editors’ note: See Case Study: Eliminating Waste From Your Team’s Decision Process for more about this process.]

- Initially focusing our efforts on one value stream. This allowed us to get the kanban/pull process up and running quickly, which in turn persuaded many of our MRP loyalists to get behind the effort. It also provided us with a cookbook for implementation with our other value streams.”

- Working with a resource who has been through this “MRP uncoupling” process before. We happened to use an outside change agent (LEAN Affiliates), but the key is the presence of an experienced professional to help avoid the pitfalls, accelerate implementation, and help pull the team together with confidence.”

Client Example: Staying Close to Operations, Part 2

Sunday, January 14th, 2007

Our client continues describing how staying close to operations helped with their problem solving (see part 1):

“When we began our lean journey a few weeks ago, we decided to start on the production floor with a specific value stream. We wanted to see results quickly, so we chose a limited scope for our initial efforts: in-house assembly and test operations.

“We started with 5S and then changed the layout to accommodate our plans for flow and pull. Our supervisors did a great job of implementing a simple visual management system so we all know how the schedule is progressing relative to takt time.

“What we didn’t expect were the parts shortages. Our Materials organization just didn’t seem able to deliver parts to support our production schedule.

“After our Gemba Walk and a review of our observations with the management team, we developed a hypothesis for what was causing our parts shortages: a mismatch between the daily pull process we implemented in assembly and our current MRP-based logistics processes.

“While we managed assembly to a level production rate based on customer demand, delivery of parts to assembly was managed by our MRP system – which in turn was driven by a master production schedule that was different than the level production rate set by Assembly. Also, lead times didn’t match the new lean assembly operation on the floor so the timing of parts delivery did not match what was needed on the floor.

“Our team now faced the question: How do we fix this problem? Many in Materials were confident that the MRP system could be adapted to support lean. They wanted to change the Master Production Schedule to match the level production rate in Assembly, while the lead times in the system could be adjusted to match the new lean processes. However, the outside change agent that we were working with, LEAN Affiliates, recommended a different approach: stop using MRP for scheduling delivery of parts and instead use a pull process across the value stream. They described a methodical approach for “uncoupling” MRP so that the ordering and movement of parts is managed as part of an integral pull process along the entire value stream. This made sense to many of us since it eliminated the use of two parts logistics systems – MRP and a pull process – but the effort of uncoupling MRP represented a radically different approach than what we were doing. We worried about the risk of disrupting production and missing customer shipments if anything went wrong.”

[Editor’s note: This story began with a perceived problem with the capacity of the AGV system, but after observing operations for a few hours this management team has discovered an underlying problem: the use of two fundamentally different logistics systems for signaling the delivery of parts.

Next post: Our client decides how to move forward.]

Client Example: Staying Close to Operations

Tuesday, January 2nd, 2007

Before the holidays, we talked about staying close to operations, and one specific habit to help do that, The Gemba Walk.

Since then, a client agreed to share his experience with us:

“My staff was reviewing the performance of an automated guided vehicle (AGV) system we implemented earlier in the year. Although initially it reduced the ‘stock to line” delivery time for parts, during the past few months delivery times were creeping back up again. Some thought we needed to increase the system’s capacity by adding a vehicle. But at the same time we knew that our volumes were steady and couldn’t understand the need for more capacity.

“So our Director of Materials and I decided to observe the delivery of parts to one of our lines during one afternoon. We parked ourselves in two different locations for four hours and watched what happened. At the end of the day we listed our most significant observations:

  1. Each AGV trip was handling only a fraction of its capacity of parts. Sometimes we would see an AGV pulling only a small box of hardware (fasteners, clips, brackets, etc.)
  2. The production lines the AGV system was supporting was down for over an hour because of a parts shortage.
  3. While the line was down due to a parts shortage, the AGV system continued to deliver parts to the line (but apparently not the parts that were ‘short’).
  4. A team lead (one of many associates who came to us to ask what we were doing) told us that since they implemented their kanban/pull system within their assembly line, the AGV System was not delivering the proper quantity or type of parts to support their schedule.
  5. Several of our Associates approached us and expressed how frustrated they are with the continual parts shortages, and the reluctance of Materials to fix the problem.
  6. There was more WIP than planned in the AGV drop zones for the line. Each drop zone overflowed with approximately twice the WIP they were designed to store.

“We then reviewed these observations with the plant manager, supervisor and team lead to create a hypothesis that would explain these observations.”

[Per our client’s request, we did not divulge the company name on the blog, but they are open to direct conversations about their experiences. Contact us to arrange this.

Next post: Our client develops a hypothesis that explains their observations.]

Is new technology really your best next investment?

Sunday, October 8th, 2006

I made a day trip to the Assembly Technology Expo in Chicago last week. What an adventure. After all, here’s an event dedicated to the latest automated innovations for manufacturing: Over 600 leading suppliers were there, from AGI Corporation (tooling and automated handling for PCB assembly) to Zierick Manufacturing (interconnection devices). I’m always fascinated with the latest technology for manufacturing, and it was fun to put my business card in all of those fish bowls and hope that I won something.

But as I looked over the Technology Pavilion and saw all of that equipment from all of those large companies, I couldn’t help but wonder…

What if American industry spent just a fraction less on material handling equipment, and just a fraction more on improving their process flow?

What if American industry spent just a fraction less on “Machine Vision Systems” (it looked really cool), and just a fraction more on teaching their people with how to see waste?

What if American industry spent just a fraction less on automated storage and retrieval systems, and just a fraction more on creating level pull and reducing inventories?

I like cool new technology just as much as the next engineer, but I sense that most companies could make much more progress by shelving their next automation project and spending that next dollar on processes, management systems, and developing people.

Manufacturing’s 5 Golden Metrics - Part 2

Tuesday, August 15th, 2006

Manufacturing performance is optimized when management recognizes that there are five golden metrics – five measures of value stream performance that really matter – and all other measurements are subordinate. Subordinate metrics may also have a great deal of importance within the factory, but optimizing performance to them is only valuable if it results in improvement to the five golden metrics.

[Editor’s note: Part 1 of Bill Waddell’s post may be viewed here.]

The big five are: Total Cost, Total Cycle Time, Delivery Performance, Quality and Safety. Activities and efforts in manufacturing that result in improving one or more of these performance measurements, without degrading performance to any of the others, are good performance. Activities and efforts that result in improvements to any other subordinate metric that do not result in improvements to any of these five, are meaningless.

The first and most significant is Total Cost, but not in any traditional sense. First, the only meaningful measurement of total cost is on a cash basis. All money spent on manufacturing must be summarized and the total compared to the previous period – not to a flexible budget or a plan. What matters is whether the total cash spent on manufacturing was more or less than it was in the previous period. It is important that this cost figure is exclusive of all allocations, and that it does not exclude S,G & A costs. The only exceptions are major capital investment spending and adjustments for Accounts Receivable and Payable. While these exceptions must be added back in to create a total lean accounting based income statement, manufacturing performance should be measured as if payment were made at the time materials and services were delivered, and payment was collected at the time finished goods were shipped to an outside customer.

The second metric is Total Cycle Time. This is calculated by studying the major purchased components and determining the total days on hand of each one. The total days on hand is the sum of all of the component in the plant regardless of its form – still in its original purchased state as raw materials, embedded in assemblies or sub-assemblies in a modified state as Work In Process Inventory, or embedded in a finished product. This total days on hand figure is divided by the planned shipments per day for all products that require that purchased component. For example, if there are 5,000 of a component in the plant in all of its various forms, and one each it goes into two final products that are each projected to ship 100 per day, the cycle time for that component in 5,000/200 = 25 days. The Total Cycle Time for the plant or for an individual value stream within the plant is the cycle time of the component with the greatest cycle time.

It is important to note that only “C” type bulk items can be excluded from this calculation, and that the Total Cycle Time is not an average cycle time, nor is it weighted in any way for the cost of the component. This is a measure of operational performance – not a financial metirc.

The third metric is Delivery Performance and it is simply the measure of the percentage of customer orders that shipped when the customer requested them to be shipped. It should not be modified in any way to accommodate company policies or shipping promises. It is purely a metric of manufacturing’s ability to meet customer requests and requirements.

Fourth is quality and this will vary by company, but it must be quality in the eyes of the customer. As a result, customer returns or warranty claims are typically the basis for this metric. It is not a summary of internal quality metrics, such as first pass yield. It is important to realize that internal quality metrics are only important to the extent that they provide information management can use to minimize cost, improve flow and meet customer quality. The only measurements of quality that truly measure operational performance are those from the customer’s perspective.

Fifth is Safety, and the standard metrics of accident/incident frequency and severity are usually sufficient.

These five measurements are manufacturing’s ‘bottom line’. All manufacturing efforts must be aimed at improving one or more of these performance indicators, without degrading performance to any of the others. All other performance metrics are subordinate to one of these, and are useful to management to the extent that they provide information necessary to improve performance to one of the Golden 5.