Our client continues describing how staying close to operations helped with their problem solving (see part 1):
“When we began our lean journey a few weeks ago, we decided to start on the production floor with a specific value stream. We wanted to see results quickly, so we chose a limited scope for our initial efforts: in-house assembly and test operations.
“We started with 5S and then changed the layout to accommodate our plans for flow and pull. Our supervisors did a great job of implementing a simple visual management system so we all know how the schedule is progressing relative to takt time.
“What we didn’t expect were the parts shortages. Our Materials organization just didn’t seem able to deliver parts to support our production schedule.
“After our Gemba Walk and a review of our observations with the management team, we developed a hypothesis for what was causing our parts shortages: a mismatch between the daily pull process we implemented in assembly and our current MRP-based logistics processes.
“While we managed assembly to a level production rate based on customer demand, delivery of parts to assembly was managed by our MRP system – which in turn was driven by a master production schedule that was different than the level production rate set by Assembly. Also, lead times didn’t match the new lean assembly operation on the floor so the timing of parts delivery did not match what was needed on the floor.
“Our team now faced the question: How do we fix this problem? Many in Materials were confident that the MRP system could be adapted to support lean. They wanted to change the Master Production Schedule to match the level production rate in Assembly, while the lead times in the system could be adjusted to match the new lean processes. However, the outside change agent that we were working with, LEAN Affiliates, recommended a different approach: stop using MRP for scheduling delivery of parts and instead use a pull process across the value stream. They described a methodical approach for “uncoupling” MRP so that the ordering and movement of parts is managed as part of an integral pull process along the entire value stream. This made sense to many of us since it eliminated the use of two parts logistics systems – MRP and a pull process – but the effort of uncoupling MRP represented a radically different approach than what we were doing. We worried about the risk of disrupting production and missing customer shipments if anything went wrong.”
[Editor’s note: This story began with a perceived problem with the capacity of the AGV system, but after observing operations for a few hours this management team has discovered an underlying problem: the use of two fundamentally different logistics systems for signaling the delivery of parts.
Next post: Our client decides how to move forward.]